Employer: Khanh My Petroleum Operating Branch (PVEPKHANH MY).

EPC Contractor: Vietsovpetro Joint Venture

Subcontractor: PTSC MC/PTSC SB.

Duration: 7/2026 – 5/2027

Description of project:

KM-WHP and DD-WHP are designed as unmanned platforms for burn down concepts and
minimum facilities.

The development of Khanh My and Dam Doi fields will comprise of the following new
facilities:
– One (1) unmanned wellhead platform KM-WHP.
– One (1) unmanned wellhead platform DD-WHP.
– 20” x 6.7 km long FWS rigid pipeline from KM-WHP to DD-WHP.

– 20” x 22.0 km long FWS rigid pipeline from DD-WHP to the existing BK-C WHRP.
– Subsea pig-gable wye fitting which has one inlet spared for Block 46-CN Development
located at tie-in point approximately 14 km downstream of DD-WHP

Sao Vang E&C is subcontractor of PTSC MC/PTSC SB. Sao Vang E&C’s scope is fabricated and installation structure of Dam Doi Platform (Total 500 tons)